“Adhering to Site Restoration Guidelines issued by Government of India, RIL submitted Bank Guarantee for Decommissioning activity for existing producing fields (D1D3 and MA),” the company said in an investor presentation post announcing its fourth quarter earnings.
RIL had till date made 19 oil and gas discoveries in the Krishna Godavri basin. Of these, MA — the only oil discovery in the block — began production in September 2008. Dhirubhai-1 and 3 (D1 and D3) fields went onstream in April 2009.
E-mails sent to RIL and its partner BP plc of UK, which holds 30 per cent stake, for comments remained unanswered.
The government’s Site Restoration Guidelines provide for a one year notice for decommissioning of facilities.
In the presentation, RIL said “average production of gas (from KG-D6 block in January-March 2018) was 4.3 million standard cubic metres per day and oil and condensate was at 1,865 barrels per day.”
The gas output, which was lower than 4.9 mmscmd in the October-December quarter of 2017, was made up of output from D1 and D3 and MA fields. It said this was due to “continuing natural decline” at the fields.
RIL had in the field development plan for D1 and D3 proposed a capital expenditure of USD 8.836 billion. For developing Dhirubhai-26 or MA oilfield, it had in 2006 proposed to invest USD 2.234 billion, which was scaled down to USD 1.96 billion in 2012.
The fields were in the investment plans supposed to last a minimum 15 years but have extinguished in less than a decade.
KG-D6 fields had hit a peak of 69.43 mmscmd in March 2010 before water and sand ingress shut down wells. This peak output comprised 66.35 mmscmd from D1 and D3, the largest of the gas discoveries on the KG-D6 block, and 3.07 mmscmd from MA field.
Besides the fall in output from D1 and D3, gas production from MA field, which had hit a peak of 6.78 mmscmd in January 2012, too has dropped.
RIL in the presentation said it is now developing three sets of discoveries — R-Cluster, Satellite Cluster and MJ fields in KG-D6 block at a cost of Rs 40,000 crore. These fields together would bring 30-35 mmscmd of peak ouput. Initial gas will begin flowing from 2020.
“R-Cluster development activities commenced; drilling to commence by 2Q FY19,” it said.